Jun302014
School completed and turned over to Rocky View Schools
May312014
Toilet partitions and washroom accessories have been installed
Installation of science room counters and fixtures has been completed
FRP wall protection has been completed in the kitchen
Final grading and landscaping has commenced
Apr302014
Installation of gymnasium hardwood flooring has commenced
Main floor lighting, HVAC and sprinkler drops is near completion
Learning Commons ceiling clouds and lighting have commenced
Exterior masonry has been completed
Mar312014
Science room fume hood has been installed
Finishing coat of paint on the second floor has been completed
Elevator has been installed
Exterior masonry is near completion
Jan312014
Ceramic tiling in main floor locker rooms is complete
Installation of second floor lockers and toilet partitions is underway
Installation of second floor lights has commenced
Dec312013
Exterior doors and hardware are being installed
Second floor painting is near completion
Exterior masonry is near completion
Nov302013
Exterior masonry veneer is near completion
Interior painting progresses
Ceramic flooring on the second floor has been completed
Interior masonry is ongoing
Oct312013
Exterior window framing and glazing is near completion
Interior painting has commenced
Main floor mechanical and electrical rough-ins are ongoing
Sep302013
Installation of light poles and concrete sidewalks has commenced
Masonry veneer is near completion
Interior drywall installation on the second floor has commenced
Fire proofing has commenced
Aug312013
Masonry veneer has commenced
Windows have been installed
Roofing is complete
Grading for site concrete and asphalt has commenced
Jul312013
Masonry exterior walls for the gymnasium and second floor interior walls continues
Exterior window frames substantially complete
Deep services for site completed
Roofing continues
Jun302013
Electrical rough-in continues
Second floor slab-on-deck is complete
Installation of second floor door frames has commenced
May312013
Installation of metal decking has been completed
Masonry construction of exterior walls is underway
Installation of underground services within the building footprint have commenced
Roofing has commenced
Apr302013
Main water service and new hydrant have been installed
Installation of metal decking commenced
Mar312013
Erection of structural steel continues
Feb282013
Grade beam installation completed
Erection of structural steel commenced
Jan312013
Pile installation has commenced
Grade beam installation has commenced
Dec312012
Construction has begun
Installation of foundation pad footings, piers and grade beams proceeds
Nov162012
Students, parents and dignitaries gather for an official ground breaking ceremony
Feb282014
Gymnasium equipment is being installed
Drywall installation and masonry are near completion
Lockers on second floor are being installed