Jun302014
School completed and turned over to Medicine Hat School District No. 76
May312014
Installation of lockers and partitions is near completion
Millwork, painting and flooring are near completion
Site grading has been completed
Hardscaping progresses
Apr302014
Installation of gymnasium equipment is near completion
Doors and hardware installation is near completion
Lighting and plumbing fixtures are being installed
Flooring and wall tiling is near completion
Mar312014
Painting of main floor walls continues
Lockers and washroom partitions have been installed
Ceramic tiling is near completion
Jan312014
Elevator is being installed
First floor painting has commenced
Plumbing, HVAC, and electrical rough-ins have commenced
Dec312013
Drywall installation on first floor is near completion
Interior painting on the second floor is near completion
Installation of second floor ceiling tile has commenced
Nov302013
Millwork on the second floor is near completion
Drywall installation on first floor has commenced
Interior painting on the second floor has commenced
Oct312013
Interior and exterior masonry are near completion
Site concrete and asphalt work has been completed
Drywall installation on second floor continues
Sep302013
High performance classrooms have been installed
Site rough grading has been completed
Site concrete and asphalt work has commenced
Drywall installation on second floor has commenced
Aug312013
Main floor framing has commenced
Roofing is complete
Installation of interior steel studs and door frames has commenced
Jul312013
Completion of second floor slabs
Roofing substantially complete
Installation of interior steel studs and door frames has commenced
Jun302013
Underground sanitary and storm rough-in has been completed
Installation of steel decking has been completed
Installation of main and second floor concrete slabs has been completed
Exterior stud framing has commenced
May312013
Erection of structural steel has been completed
Parapet framing has commenced
May012013
Students, parents and dignitaries gathered for an official sod turning and naming ceremony
Apr302013
Erection of structural steel continues
Exterior masonry work commenced
Mar312013
Installation of grade beams has been completed
Erection of structural steel has commenced
Feb282013
Installation of concrete piling completed
Grade beams installation commenced
Jan312013
Installation of concrete piling has commenced
Dec312012
Construction has begun
Site preparation is completed
Feb282014
Drywall installation is near completion
Mechanical room equipment is being installed
Plumbing, HVAC, and electrical rough-ins are near completion
Jun042014
Installation of lockers and partitions is near completion
Millwork, painting and flooring are near completion
Site grading has been completed
Hardscaping progresses