Jun192014
School completed and turned over to Red Deer Catholic Regional Schools
May312014
Hardscaping has been completed
Interior signs have been installed
Motorized blinds have been installed
Acoustical wall panels are in place
Apr302014
Fire alarm has been installed
Light fixtures have been installed
Lockers have been installed
Parking lots curbs are in place
Mar312014
Installation of ceiling system is near completion
Finishing coat of paint progresses
Millwork installation progresses
Jan312014
Installation of ceiling system has commenced
Interior painting progresses
Floor finishing has commenced
Dec312013
Installation of drywall continues
Primer painting has commenced
Mechanical and electrical rough-ins have commenced
Nov302013
Installation of drywall progresses
Floor polishing continues
Oct312013
Installation of drywall has commenced
Floor polishing has commenced
Electrical rough-in has commenced
Sep302013
Installation of windows has commenced
Parking lot installation has been completed
Interior and exterior masonry has commenced
Aug312013
Installation of the roofing system is ongoing
Installation of the parking lot has commenced
Structural steel is complete
Jul312013
Installation of the roofing system has commenced
Installation of underground utilities: electrical, storm and sanitary – foot print of building
Structural steel installation continues
Jun302013
Erection of structural steel has commenced
Installation of parking lot sub-grades is ongoing
May312013
Installation of foundation insulation and backfill has commenced
Grade beams installation continues
Installation of underground utilities continues
Apr302013
Installation of foundation pads and piers commenced
Grade beams installation is underway
Installation of underground utilities commenced
Mar312013
Site trailer and fencing have been installed
Site preparation for excavation has commenced
Dec312012
Site preparation has begun
Oct122012
Official sod turning ceremony and blessing of the site by Deacon Claude Baril
Feb282014
Installation of ceiling system is near completion
Finishing coat of paint progresses
Millwork installation progresses