Jun182014
School completed and turned over to Red Deer Public Schools
May312014
Trees have been planted and black dirt is ready for sod
Interior signage has been installed
Bike racks and garbage bins have been installed
Sidewalks have been completed
Apr302014
Gymnasium lines have been painted
Gymnasium divider curtain has been installed
Acoustic walls have been installed
Parking lot curbs are in place
Mar312014
Installation of doors and hardware has been completed
Interior painting has been completed
Hardwood has been installed
Plumbing fixtures have been installed
Jan312014
Installation of millwork progresses
Interior painting progresses
Floor finishing has commenced
Dec312013
Installation of doors and hardware has commenced
Window trim has been completed
Painting of final coat is near completion
Nov302013
Installation of millwork has commenced
Installation of the ceiling system progresses
Mechanical work piping, ducting and equipment has commenced
Oct312013
Installation of doors and hardware has commenced
Flooring polishing has commenced
Indoor painting progresses
Landscaping continues
Sep302013
High performance classrooms have been installed
Site work for the parking lot continues
Drywall installation in the gymnasium has commenced
Aug312013
Installation of drywall is ongoing
Site work for the parking lot has commenced
Installation of venting and ductwork has commenced
Painting of primer and first coat has commenced
Jul312013
Interior framing and stud installation is ongoing
Site work for the parking lot commenced
Installation of the roofing system commenced
Jun302013
Interior and exterior masonry of the gymnasium has commenced
Installation of parapet walls has commenced
Electrical rough-in is ongoing
May312013
Erection of structural steel continues
Installation of underground services within the building footprint has commenced
Apr302013
Erection of structural steel commenced
Mar312013
Underground utilities (electrical, storm and sanitary) have been installed
Feb282013
Construction of grade beams, pads and piers completed
Dec312012
Site preparation has begun
Feb282014
Installation of doors and hardware is near completion
Interior painting is completed
Basketball hoops have been installed